Prefeasibility Study

On August 20, 2014, Atacama Pacific announced the results of a Prefeasibility Study (“PFS”) for the Cerro Maricunga oxide gold project following up on the Preliminary Economic Assessment published on January 12, 2013. The PFS demonstrated the economic viability of an open pit and conventional heap leach operation at Cerro Maricunga as highlighted below:
  • Average annual production over the first 8 years of 281,000 gold ounces
  • 2.96 million recoverable gold ounces over a 13 year mine life
  • Average cash costs of $683 per ounce
  • Initial capital costs of $398.9 million with sustaining capital of $187.6 million
  • Strong total operating cash flows of $1.27 billion at $1,350 per ounce gold (“/oz Au”)
PEA Technical Highlights
Mine Type Open Pit
Mine Life 13 Years
Life of Mine Reserves 294.4 M tonnes
Life of Mine Gold Production 2.96 M ounces
First 8 Years Average Production 281,000 ounces
Life of Mine Average Gold Production 228,000 ounces
Average Gold Grade 0.40 g/t
Processing Conventional Heap Leach
Daily Throughput 80,000 tonnes
Strip Ratio (Waste: Ore) 1.76:1
Crush Size 19 mm (3/4 in)
Gold Recovery 79.2%
Life of Mine Cash Costs US$ 683/oz Au
Initial Capex $389.9 M
Sustaining Capital $187.6 M
Chilean Tax Rate 20%

Top

Economic Analysis

The PFS calculates a base-case after-tax NPV at a 5% discount rate of US$409.3 million with an after-tax IRR of 25.0% and an average pre-tax cash flow from operations of US$108.7 million over the first 8 years of operation. See the table below.

The following operational parameters and costs were used in the PFS:

  Processing Rate: 80,000 tonnes per day
  Gold Recovery: 79.2%
  Average Mining Cost: $1.40 per tonne mined
  Processing costs: $2.52 per tonne processed
  General and Administration: $0.54 per tonne processed
  Gold Price: $1,350/oz Au

PFS Economics Summary
Top

Mining and Processing

Projected total gold production over the projected 13-year mine life is 2.93 million ounces at an average operating cash cost of $683/oz Au. Gold production begins to decline in Year 9 as the mining activities increase in depth in the pit; however, the reduction in mined ore is partially offset by increasing gold grades at depth. Approximately 294.4 million tonnes of ore grading 0.40 g/t gold will be mined through open pit methods and processed on a conventional heap leach pad. An average life of mine strip ratio of 1.76 to 1 (waste to resource) was calculated.

Conventional open pit mining methods have been considered in mining the Cerro Maricunga deposit. The PFS considers utilizing a maximum fleet of,
  • 17 290-tonne haul trucks (Komatsu 9300E–4SE),
  • 4 42-cubic metre hydraulic shovels (Komatsu PC8000),
  • 5 production drills (Atlas PV 275),
along with various ancillary equipment to achieve the maximum annual total ore and waste movement of 94 million tonnes. The PFS takes into account that the mining fleet will be leased and Atacama Pacific has received a proposed lease agreement.

The Mining and Process Schedule is provided below.

Mining and Production Schedule

Cerro Maricunga Operations Plan, 2014 PFS

Cerro Maricunga Operations Plan, 2014 PFS


Processing
Oxide mineralization will be trucked to a primary gyratory crusher facility (METSO MK II 62” x 75”), located immediately west of the pit boundary where it will be crushed to 165 millimetres (“mm”). The primary crushed material will then be conveyed approximately 2.9 kilometres (“km”) to feed two secondary cone crushers (METSO MP 1000) and three tertiary cone crushers (METSO MP 800). The final crushed product, measuring (P80) 19 mm, will be conveyed 2.4 km to the heap leach pads.

Crushed material will be stacked on the heap leach pad by a radial stacker in 50 by 50 m modules in layers 10 m thick. The final leach pad height will be approximately 100 m. A pad irrigation rate of 10 liters/hour/metre2 has been considered. NaCN and lime consumption are expected to be 0.23 kg/t”) and 2.7 kg/t respectively. The cost of consumables was established from recent quotes provided by Chilean-based suppliers. The pregnant leaching solution containing gold will be pumped to a conventional carbon adsorption facility (ADR plant) where gold from process solutions is recovered to a final gold doré product.

Secondary / Tertiary Crushers
Secondary / Tertiary Crushers

Location of Leach Pads
Location of Leach Pads

Location of Rock Waste Storage (right) with Phoenix Zone (left)
Location of Rock Waste Storage (right) with Phoenix Zone (left)
Top

Capital Requirements

The PFS calcalates capital expenditures for the development of an open pit mining and conventional heap leach processing operation at the Cerro Maricunga project at US$398.9 million, which includes contingencies of US$46.5 million. A breakdown of the capital costs is provided in the table below. Additional capital requirement during the life of the mine, including annual heap leach pad expansions and closure costs total US$187.6 million, which includes a 15% contingency. The capital costs presented are based on quotes received from equipment manufactures or contractors.

Summary of Initial Capital Expenditures1 *
Item US$ (millions)
Mine  
     Pre-strip 15.3
    1st Fleet Lease Payment 7.5
    Mining Support 19.6
Processing  
    Primary Crushers & Stockpile 34.2
    Secondary Crushers 18.0
    Tertiary Crushers 20.5
    Tertiary Screening Plant 18.3
    Fine Stockpile 14.5
    Conveyors 37.8
    Leach Pads 83.7
    ADR & EW/Smelting 23.3
    First Fill 2.0
Infrastructure  
Support Facilities 34.9
Roads 10.1
Owners 12.7
Capital Costs (without contingencies) 352.5
Contingencies (15%)2 46.5
Total Capital 398.9
1. The PFS was completed to a level of accuracy of +20% to -5%
2. Contingencies are 15% of capital costs excluding "Mine" costs


Leasing

The PEA assumes, on the basis of quotes received, that the mining fleet will be acquired through a manufacturer lease arrangement for a total cost of US$234.4 million. The quote is for a lease period of 5 years for the drilling/loading/hauling fleet with a final payment in following year for the purchase of the fleet. The auxiliary equipment lease is for a period of 3 years with a payment in the fourth year for final purchase.

The construction of a truck maintenance shop will be undertaken by ARRIGONI under a $28.4 million leaseback over a period of 13 years.

Atacama Pacific has been provided a letter of intent from ELECNOR, a multinational engineering and construction firm, for the construction and operation of the water supply infrastructure from Copiapó to Cerro Maricunga. The annual cost of the lease is $17.5 million for the first 8 years and declines to $10 million in year 13, reflecting lower ore throughput. The same firm has offered to construct and operate the electrical distribution system at a price of $5 million per year.